DELAY DISCLAIMER NOT ENFORCED, CONTRACTORS RECOVER FOR LOST PRODUCTIVITY


Court of Appeals of Tennessee, at Nashville

Lee Masonry, Inc. v. City of Franklin

No. M2008-02844
April 28, 2010



Overview

A Tennessee court has ruled that an owner could not enforce a no-damage-for-delay clause on a multiple prime contract project. The delay and disruption were caused by the owner's failure to meet its contractual obligations to schedule and ... Log in to view the full text.

 